6B.1 Test system architecture
37.571-43GPPPart 4: Test suitesRelease 16TSUser Equipment (UE) conformance specification for UE positioning
6B.1.1 General system architecture
Refer to 3GPP TS 36.523-3 [6], clause 4.1.1.
6B.1.2 Component architecture
The NR PTC is controlled by the TTCN-3 positioning master test component (POS MTC) which:
– Is an extension of the MTC as defined in 3GPP TS 38.523-3 [24], clause 4.2.
– Controls the SS Positioning Simulator.
Figure 6B.1.2-1: Component architecture for a NR scenario
As specified in TS 37.571-2 [2], subclause 8.2.8:
– The connection between the Position Simulator and the UE (Satellite signal) shall be conducted.
– The connection between the System Simulator and the UE (Radio Interface) shall be conducted for NR FR1 and radiated (OTA) for NR FR2.