13.5 UE RRC Procedure Performance
25.3313GPPProtocol specificationRadio Resource Control (RRC)Release 17TS
This subclause defines the performance requirements related to RRC procedures in the UE. Where the total delay is impacted by processing of variable length on the physical layer (e.g. physical layer synchronisation), references to appropriate specifications are given.
13.5.1 Definitions
The following definitions of N1 and N2 are valid only for this UE RRC Procedure Performance specification.
N1 = upper limit on the time required to execute modifications in UE after the reception of a UTRAN -> UE message has been completed. Where applicable (e.g. the physical layer transmission is impacted), the changes shall be adopted in the beginning of the next TTI starting after N1. N1 is specified as a multiple of 10 ms.
N2 = number of 10 ms radio frames from end of reception of UTRAN -> UE message on UE physical layer before the transmission of the UE -> UTRAN response message must be ready to start on a transport channel with no access delay other than the TTI alignment (e.g. DCH, therefore excluding delays caused by RACH procedure etc). The UE response message transmission from the physical layer shall begin at the latest (N2*10)+TTI ms after completion of the reception of the last TTI carrying the triggering UTRAN -> UE message. When Target State is CELL_DCH, the UE response message transmission from the physical layer may be additionally delayed by the value of IE "SRB delay".
N1 and N2 are independent (e.g. N2-N1 is not restricted to being less than or equal to 10ms).
13.5.2 RRC procedure performance values
NOTE: Times indicated in the table do not include cell reselection.
|
Procedure title: |
UTRAN -> UE |
UE -> UTRAN |
N1 |
N2 |
Notes |
|---|---|---|---|---|---|
|
RRC Connection Management Procedures |
|||||
|
Broadcast of system information |
SYSTEM INFORMATION |
N2 is not applicable for any system information messages, because there is no response message from the UE. |
|||
|
Master Information Block |
SYSTEM INFORMATION |
5 |
NA |
No system information data shall be lost due to processing of a MIB received with no detectable errors. This means that the UE shall buffer all system information data received after the MIB until the data can be processed according to the information in the MIB, unless the MIB was received erroneously. |
|
|
System Information Block type 1 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 2 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 3 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 4 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 5 or System Information Block type 5bis |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 6 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 7 |
SYSTEM INFORMATION |
5 |
NA |
||
|
System Information Block type 11 or System Information Block type 11bis |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 11ter |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 12 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 13 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 14 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 15 or 15bis or 15.1 or 15.1bis or 15.1ter or 15.2 or 15.2bis or 15.2ter or 15.3 or 15.3bis or 15.4 or 15.5 or 15.6 or 15.7 or 15.8 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 16 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 18 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 19 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 20 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 21 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 22 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 23 |
SYSTEM INFORMATION |
10 |
NA |
||
|
System Information Block type 24 |
SYSTEM INFORMATION |
5 |
NA |
||
|
System Information Block type 25 |
SYSTEM INFORMATION |
5 |
NA |
||
|
System Information Change Indication |
SYSTEM INFORMATION |
10 |
NA |
||
|
RRC connection establishment Target state CELL_DCH |
RRC CONNECTION SETUP |
RRC CONNECTION SETUP COMPLETE |
10 |
NA |
N1 measures time to the start of tx / rx on DPCH. N2 cannot be specified, because RRC CONNECTION SETUP COMPLETE message is transmitted only after physical layer synchronisation, which also depends on the Node B. The performance of the physical layer synchronisation procedure is specified in [19] and [20] |
|
RRC connection establishment Target state CELL_FACH |
RRC CONNECTION SETUP |
RRC CONNECTION SETUP COMPLETE |
10 |
11 |
N1 and N2 applicable as defined (N2 can be tested from the initiation of the power ramp on RACH). |
|
RRC connection release From CELL_DCH state |
RRC CONNECTION RELEASE |
RRC CONNECTION RELEASE COMPLETE |
5 |
8 |
N1 sets the requirement for the time from the completion of the last repetition of the RRC CONNECTION RELEASE COMPLETE message to the release of the physical channel. N2 sets the requirement from the end of successful reception of the RRC CONNECTION RELEASE message to the start of the first transmission of the RRC CONNECTION RELEASE COMPLETE message. |
|
RRC connection release From CELL_FACH state |
RRC CONNECTION RELEASE |
RRC CONNECTION RELEASE COMPLETE |
NA |
11 |
N1 represents UE internal configuration that cannot be externally observed. |
|
Paging |
PAGING TYPE 1 |
CELL UPDATE |
10 |
11+T |
T is the repetition period of SIB7 (applicable for FDD) and SIB14 (applicable for TDD) |
|
UE capability enquiry |
UE CAPABILITY ENQUIRY |
UE CAPABILITY INFORMATION |
NA |
8 |
N1 is not applicable because the UE configuration does not change. |
|
Security mode control |
SECURITY MODE COMMAND |
SECURITY MODE COMPLETE |
5 |
8 |
|
|
Signalling connection release procedure |
SIGNALLING CONNECTION RELEASE |
5 |
NA |
N2 is not applicable because there is no response message. |
|
|
Counter check |
COUNTER CHECK |
COUNTER CHECK RESPONSE |
NA |
8 |
N1 is not applicable because the UE configuration does not change. |
|
ETWS Primary Notification with Security |
ETWS PRIMARY NOTIFICATION WITH SECURITY |
10 |
NA |
N2 is not applicable because there is no response message. |
|
|
Radio Bearer control procedures |
|||||
|
Radio bearer establishment Target state CELL_DCH |
RADIO BEARER SETUP |
RADIO BEARER SETUP COMPLETE / FAILURE |
10 |
NA |
N2 cannot be specified, because the RADIO BEARER SETUP COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. |
|
Radio bearer establishment From state CELL_FACH to state CELL_FACH |
RADIO BEARER SETUP |
RADIO BEARER SETUP COMPLETE / FAILURE |
10 |
11 |
|
|
Radio bearer establishment From CELL_DCH to CELL_FACH |
RADIO BEARER SETUP |
RADIO BEARER SETUP COMPLETE |
NA |
NA |
N1 and N2 cannot be specified, because UE need to read SIBs on BCH before sending RADIO BEARER SETUP COMPLETE |
|
Radio bearer reconfiguration Target state CELL_DCH |
RADIO BEARER RECONFIGURATION |
RADIO BEARER RECONFIGURATION COMPLETE / FAILURE |
5 or 10 |
NA |
N2 cannot be specified, because the RADIO BEARER RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. NOTE 1 |
|
Radio bearer reconfiguration From Idle Mode and state CELL_FACH to state CELL_DCH |
RADIO BEARER RECONFIGURATION |
RADIO BEARER RECONFIGURATION COMPLETE / FAILURE |
10 |
11 |
This requirement applies when the UE has a common E-DCH resource and is not required to perform any synchronization. |
|
Radio bearer reconfiguration From state CELL_FACH to state CELL_FACH |
RADIO BEARER RECONFIGURATION |
RADIO BEARER RECONFIGURATION COMPLETE / FAILURE |
10 |
11 |
|
|
Radio bearer reconfiguration From state CELL_DCH to state CELL_FACH |
RADIO BEARER RECONFIGURATION |
RADIO BEARER RECONFIGURATION COMPLETE |
NA |
NA |
N1 and N2 cannot be specified, because UE need to read SIBs on BCH before sending RADIO BEARER RECONFIGURATION COMPLETE |
|
Radio bearer release Target state CELL_DCH |
RADIO BEARER RELEASE |
RADIO BEARER RELEASE COMPLETE / FAILURE |
10 |
11 |
|
|
Radio bearer release From state CELL_FACH to state CELL_FACH |
RADIO BEARER RELEASE |
RADIO BEARER RELEASE COMPLETE / FAILURE |
10 |
11 |
|
|
Radio bearer release From state CELL_DCH to state CELL_FACH |
RADIO BEARER RELEASE |
RADIO BEARER RELEASE COMPLETE |
NA |
NA |
N1 and N2 cannot be specified, because UE need to read SIBs on BCH before sending RADIO BEARER RECONFIGURATION COMPLETE |
|
Transport channel reconfiguration Target state CELL_DCH |
TRANSPORT CHANNEL RECONFIGURATION |
TRANSPORT CHANNEL RECONFIGURATION COMPLETE / FAILURE |
5 or 10 |
NA |
N2 cannot be specified, because the TRANSPORT CHANNEL RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. NOTE 1 |
|
Transport channel reconfiguration From state CELL_FACH to state CELL_FACH |
TRANSPORT CHANNEL RECONFIGURATION |
TRANSPORT CHANNEL RECONFIGURATION COMPLETE / FAILURE |
10 |
11 |
|
|
Transport channel reconfiguration From state CELL_DCH to state CELL_FACH |
TRANSPORT CHANNEL RECONFIGURATION |
TRANSPORT CHANNEL RECONFIGURATION COMPLETE |
NA |
NA |
N1 and N2 cannot be specified, because UE need to read SIBs on BCH before sending TRANSPORT CHANNEL RECONFIGURATION COMPLETE |
|
Transport format combination control AM or UM RLC mode |
TRANSPORT FORMAT COMBINATION CONTROL |
TRANSPORT FORMAT COMBINATION CONTROL FAILURE |
5 |
8 |
|
|
Transport format combination control Transparent mode |
TRANSPORT FORMAT COMBINATION CONTROL |
5 |
NA |
N2 is not applicable because no response message is defined. |
|
|
Physical channel reconfiguration Target state CELL_DCH |
PHYSICAL CHANNEL RECONFIGURATION |
PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE |
5 or 8 |
NA |
N2 cannot be specified, because the PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. NOTE 1 |
|
Physical channel reconfiguration From state CELL_FACH to state CELL_FACH |
PHYSICAL CHANNEL RECONFIGURATION |
PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE |
8 |
9 |
|
|
Physical channel reconfiguration From state CELL_DCH to state CELL_FACH |
PHYSICAL CHANNEL RECONFIGURATION |
PHYSICAL CHANNEL RECONFIGURATION COMPLETE |
NA |
NA |
N1 and N2 cannot be specified, because UE need to read SIBs on BCH before sending PHYSICAL CHANNEL RECONFIGURATION COMPLETE |
|
Physical Shared Channel Allocation [TDD only] |
PHYSICAL SHARED CHANNEL ALLOCATION |
5 |
NA |
N2 is not applicable because no response message is defined. |
|
|
Uplink Physical Channel Control [TDD only] |
UPLINK PHYSICAL CHANNEL CONTROL |
8 |
NA |
Requirements for outer loop and timing advance adjustments are defined in [22] and [20]. N2 is not applicable because there is no response message. |
|
|
RRC connection mobility procedures |
|||||
|
Cell update |
CELL UPDATE CONFIRM |
UTRAN MOBILITY INFORMATION CONFIRM |
5 |
8 |
|
|
PHYSICAL CHANNEL RECONFIGURATION COMPLETE Target state CELL_FACH |
8 |
9 |
|||
|
PHYSICAL CHANNEL RECONFIGURATION COMPLETE Target state CELL_DCH |
8 |
NA |
N2 cannot be specified, because the PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. |
||
|
TRANSPORT CHANNEL RECONFIGURATION COMPLETE Target state CELL_FACH |
10 |
11 |
|||
|
TRANSPORT CHANNEL RECONFIGURATION COMPLETE Target state CELL_DCH |
10 |
NA |
N2 cannot be specified, because the PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. |
||
|
RADIO BEARER RECONFIGURATION COMPLETE Target state CELL_FACH |
10 |
11 |
|||
|
RADIO BEARER RECONFIGURATION COMPLETE Target state CELL_DCH |
10 |
NA |
N2 cannot be specified, because the PHYSICAL CHANNEL RECONFIGURATION COMPLETE / FAILURE message is transmitted only after physical layer synchronisation, which depends also on Node B. |
||
|
RADIO BEARER RELEASE COMPLETE Target state CELL_DCH |
10 |
11 |
|||
|
URA update |
URA UPDATE CONFIRM |
UTRAN MOBILITY INFORMATION CONFIRM |
5 |
8 |
|
|
UTRAN mobility information |
UTRAN MOBILITY INFORMATION |
UTRAN MOBILITY INFORMATION CONFIRM / FAILURE |
5 |
8 |
|
|
Active set update |
ACTIVE SET UPDATE |
ACTIVE SET UPDATE COMPLETE / FAILURE |
NA |
5 |
The requirements on UE combining and power control performance for both UL and DL are specified by RAN WG4 in [21] and [19]. Also in case of branch addition the COMPLETE / FAILURE message is transmitted without waiting for the new branch to stabilise, therefore N2 is specified. |
|
Inter-RAT handover to UTRAN |
HANDOVER TO UTRAN COMMAND (other system) |
HANDOVER TO UTRAN COMPLETE |
NA |
NA |
The performance of this procedure is specified in 3GPP TS 45.010 in case of handover from GSM and 3GPP TS 36.133 in case of handover from E-UTRA. |
|
Inter-RAT handover from UTRAN |
HANDOVER FROM UTRAN COMMAND |
HANDOVER FROM UTRAN FAILURE |
NA |
NA |
The performance of this procedure is specified in [19] and [20]. |
|
Measurement procedures |
|||||
|
Measurement control |
MEASUREMENT CONTROL |
MEASUREMENT CONTROL FAILURE |
5 |
8 |
Response to measurement inquiry depends on physical layer measurement. Response time is defined in [19] and [20]. N1 and N2 only define the processing of the message. |
|
UE INFORMATION |
|||||
|
UE INFORMATION |
UE INFORMATION REQUEST |
UE INFORMATION RESPONSE |
5 |
8 |
NOTE 1: The lower value applies when the UE is ordered to do a serving HS-DSCH cell change, changing no other information than contained in the IE "H-RNTI", the IE "Downlink HS-PDSCH information", the IE "Uplink DPCH power control info" and/or the IE "Serving HS-DSCH radio link indicator" (FDD only).