5 Examples of structured procedures

3GPP44.057CTS supervising system layer 3 specificationGSM Cordless Telephony System (CTS), Phase 1Release 17TS

Clause 5 is informative.

5.1 CTS-FP Initialisation

The CTS-FP initialisation procedure is always initiated by the fixed part.

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| CTS-SPM INITIALISATION REQUEST |

| ───────────────────────────────────────> | Service request

| |

+── ──+

+── ──+

| CTS-SPM FP AUTHENTICATION REQUEST | FP

| <─────────────────────────────────────── | authentication

| CTS-SPM FP AUTHENTICATION RESPONSE |

| ───────────────────────────────────────> |

+── ──+

+── ──+

| CTS-SPM INITIALISATION ACCEPT |

| <─────────────────────────────────────── |

+── ──+

+── ──+

| CTS-SPM SN SIGNING MODE COMMAND |

| <─────────────────────────────────────── | Signature mode setting

+── ──+

+── ──+

| CTS-SPM OPERATION DATA REQUEST |

| ───────────────────────────────────────> | Data transmission

| CTS-SPM OPERATION DATA DELIVER |

| <─────────────────────────────────────── |

+── ──+

+── ──+

| CTS-SPM INITIALISATION COMPLETE |

| ───────────────────────────────────────> |

+── ──+

Figure 5.1/GSM 04.xx: CTS-FP initialisation

5.2 CTS-SPM Enrolment

The CTS-SPM enrolment procedure is always initiated by the fixed part following an initiation by the mobile station.

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| CTS-SPM ENROLMENT REQUEST

| ───────────────────────────────────────> | Service request

| |

+── ──+

+── ──+

| CTS-SPM FP AUTHENTICATION REQUEST | FP

| <─────────────────────────────────────── | authentication

| CTS-SPM FP AUTHENTICATION RESPONSE |

| ───────────────────────────────────────> |

+── ──+

+── ──+

| CTS-SPM MS AUTHENTICATION REQUEST | MS

| <─────────────────────────────────────── | authentication

| CTS-SPM MS AUTHENTICATION RESPONSE |

| ───────────────────────────────────────> |

+── ──+

+── ──+

| CTS-SPM ENROLMENT ACCEPT |

| <─────────────────────────────────────── |

+── ──+

Figure 5.2/GSM 04.xx: CTS-SPM Enrolment

5.3 Operation data update

The operation data update procedure is always initiated by the fixed part.

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| CTS-SPM OPERATION DATA REQUEST |

| ───────────────────────────────────────> | Service request

+── ──+

+── ──+

| CTS-SPM FP AUTHENTICATION REQUEST | FP

| <─────────────────────────────────────── | authentication

| CTS-SPM FP AUTHENTICATION RESPONSE |

| ───────────────────────────────────────> |

+── ──+

+── ──+

| CTS-SPM SN SIGNING MODE COMMAND |

| <─────────────────────────────────────── | Signature mode setting

+── ──+

+── ──+

| CTS-SPM OPERATION DATA DELIVER |

| <─────────────────────────────────────── |

+── ──+

+── ──+

| CTS-SPM OPERATION DATA ACCEPT |

| ───────────────────────────────────────> |

+── ──+

Figure 5.3/GSM 04.xx: CTS operation data update

5.4 Information request

The information request procedure is always initiated by the service node (the CTS-FP/CTS-SN connection is initiated by the fixed part).

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| | Other procedure

+── ──+

+── ──+

| CTS-SPM INFORMATION DATA REQUEST |

| <─────────────────────────────────────── | Information transmission

| CTS-SPM INFORMATION DATA RESPONSE |

| ───────────────────────────────────────> |

+── ──+

Figure 5.4/GSM 04.xx: Information request procedure

5.5 CTS-FP De-initialisation

The CTS-FP de-initialisation procedure is always initiated by the service node (the CTS-FP/CTS-SN connection is initiated by the fixed part).

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| | Other procedure

+── ──+

+── ──+

| CTS-SPM DE-INITIALISATION REQUEST |

| <─────────────────────────────────────── |

| CTS-SPM DE-INITIALISATION COMPLETE |

| ───────────────────────────────────────> |

+── ──+

Figure 5.5/GSM 04.xx: CTS-FP De-initialisation procedure

5.6 CTS-SPM De-enrolment

The de-enrolment procedure can be either initiated by the fixed part or by the service node.

5.6.1 CTS-SPM De-enrolment initiated by the fixed part

The de-enrolment indication is sent by the fixed part to the service node.

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| CTS-SPM DE-ENROLMENT INDICATION |

| ───────────────────────────────────────> |

+── ──+

Figure 5.6/GSM 04.xx: CTS-SPM De-enrolment indication

5.6.2 CTS-SPM De-enrolment initiated by the service node

The de-enrolment request is sent by the service node.

Fixed Part Service Node

+── ──+

| | CTS-FP/CTS-SN connection

+── ──+

+── ──+

| | Other procedure

+── ──+

+── ──+

| CTS-SPM DE-ENROLMENT REQUEST |

| <─────────────────────────────────────── |

| CTS-SPM DE-ENROLMENT COMPLETE |

| ───────────────────────────────────────> |

+── ──+

Figure 5.7/GSM 04.xx: CTS-SPM De-enrolment request