8 NRPPa procedures
38.4553GPPNG-RANNR Positioning Protocol A (NRPPa)Release 17TS
8.1 Elementary procedures
In the following tables, all EPs are divided into Class 1 and Class 2 EPs.
Table 8.1-1: Class 1 Elementary Procedures
Elementary Procedure |
Initiating Message |
Successful Outcome |
Unsuccessful Outcome |
|
---|---|---|---|---|
Response message |
Response message |
|||
E-CID Measurement Initiation |
E-CID MEASUREMENT INITIATION REQUEST |
E-CID MEASUREMENT INITIATION RESPONSE |
E-CID MEASUREMENT INITIATION FAILURE |
|
OTDOA Information Exchange |
OTDOA INFORMATION REQUEST |
OTDOA INFORMATION RESPONSE |
OTDOA INFORMATION FAILURE |
|
Positioning Information Exchange |
POSITIONING INFORMATION REQUEST |
POSITIONING INFORMATION RESPONSE |
POSITIONING INFORMATION FAILURE |
|
TRP Information Exchange |
TRP INFORMATION REQUEST |
TRP INFORMATION RESPONSE |
TRP INFORMATION FAILURE |
|
Measurement |
MEASUREMENT REQUEST |
MEASUREMENT RESPONSE |
MEASUREMENT FAILURE |
|
Positioning Activation |
POSITIONING ACTIVATION REQUEST |
POSITIONING ACTIVATION RESPONSE |
POSITIONING ACTIVATION FAILURE |
|
PRS Configuration Exchange |
PRS CONFIGURATION REQUEST |
PRS CONFIGURATION RESPONSE |
PRS CONFIGURATION FAILURE |
|
Measurement Preconfiguration |
MEASUREMENT PRECONFIGURATION REQUIRED |
MEASUREMENT PRECONFIGURATION CONFIRM |
MEASUREMENT PRECONFIGURATION REFUSE |
Table 8.1-2: Class 2 Elementary Procedures
Elementary Procedure |
Initiating Message |
---|---|
E-CID Measurement Failure Indication |
E-CID MEASUREMENT FAILURE INDICATION |
E-CID Measurement Report |
E-CID MEASUREMENT REPORT |
E-CID Measurement Termination |
E-CID MEASUREMENT TERMINATION COMMAND |
Error Indication |
ERROR INDICATION |
Assistance Information Control |
ASSISTANCE INFORMATION CONTROL |
Assistance Information Feedback |
ASSISTANCE INFORMATION FEEDBACK |
Positioning Information Update |
POSITIONING INFORMATION UPDATE |
Measurement Report |
MEASUREMENT REPORT |
Measurement Update |
MEASUREMENT UPDATE |
Measurement Abort |
MEASUREMENT ABORT |
Measurement Failure Indication |
MEASUREMENT FAILURE INDICATION |
Positioning Deactivation |
POSITIONING DEACTIVATION |
Measurement Activation |
MEASUREMENT ACTIVATION |
8.2 Location Information Transfer Procedures
8.2.1 E-CID Measurement Initiation
8.2.1.1 General
The purpose of E-CID Measurement Initiation procedure is to allow the LMF to request the NG-RAN node to report E-CID measurements used by LMF to compute the location of the UE.
8.2.1.2 Successful Operation
Figure 8.2.1.2-1: E-CID Measurement Initiation procedure, successful operation
The LMF initiates the procedure by sending an E-CID MEASUREMENT INITIATION REQUEST message. If the NG-RAN node is able to initiate the requested E-CID measurements, it shall reply with the E-CID MEASUREMENT INITIATION RESPONSE message.
The Measured Results IE shall be included in the E-CID Measurement Result IE of the E-CID MEASUREMENT INITIATION RESPONSE message when measurement results other than the "Cell-ID" have been requested.
If the Report Characteristics IE is set to "OnDemand", the NG-RAN node shall return the result of the measurement in the E-CID MEASUREMENT INITIATION RESPONSE message including, if available, the NG-RAN Access Point Position IE in the E-CID Measurement Result IE, and the LMF shall consider that the E-CID measurements for the UE has been terminated by the NG-RAN node. If available, the NG-RAN node shall include the Cell Portion ID IE in the E-CID MEASUREMENT INITIATION RESPONSE message. Upon reception of the Cell Portion ID IE, the LMF may use the value as the cell portion for the measurement. If the Report Characteristics IE is set to "OnDemand" and the Inter-RAT Measurement Quantities IE is included in the E-CID MEASUREMENT INITIATION REQUEST message, the NG-RAN node shall, if supported, provide the corresponding measurements, if available in the NG-RAN node, in the Inter-RAT Measurement Result IE in E-CID MEASUREMENT INITIATION RESPONSE message. If the Report Characteristics IE is set to "OnDemand" and the WLAN Measurement Quantities IE is included in the E-CID MEASUREMENT INITIATION REQUEST message, the NG-RAN node shall, if supported, provide the corresponding measurements, if available in the NG-RAN node, in the WLAN Measurement Result IE in E-CID MEASUREMENT INITIATION RESPONSE message.
If the Report Characteristics IE is set to "Periodic", the NG-RAN node shall initiate the requested measurements and shall reply with the E-CID MEASUREMENT INITIATION RESPONSE message without including either the E-CID Measurement Result IE or the Cell Portion ID IE in this message. The NG-RAN node shall then periodically initiate the E-CID Measurement Report procedure for the measurements, with the requested reporting periodicity.
8.2.1.3 Unsuccessful Operation
Figure 8.2.1.3-1: E-CID Measurement Initiation procedure, unsuccessful operation
If the NG-RAN node is not able to initiate at least one of the requested E-CID measurements, the NG-RAN node shall respond with an E-CID MEASUREMENT INITIATION FAILURE message.
8.2.1.4 Abnormal Conditions
Void.
8.2.2 E-CID Measurement Failure Indication
8.2.2.1 General
The purpose of the E-CID Measurement Failure Indication procedure is for the NG-RAN node to notify the LMF that the E-CID measurements previously requested with the E-CID Measurement Initiation procedure can no longer be reported.
8.2.2.2 Successful Operation
Figure 8.2.2.2-1: E-CID Measurement Failure Indication, successful operation
Upon reception of the E-CID MEASUREMENT FAILURE INDICATION message, the LMF shall consider that the E-CID measurements for the UE have been terminated by the NG-RAN node.
8.2.2.3 Unsuccessful Operation
Not applicable.
8.2.2.4 Abnormal Conditions
Void.
8.2.3 E-CID Measurement Report
8.2.3.1 General
The purpose of E-CID Measurement Report procedure is for the NG-RAN node to provide the E-CID measurements for the UE to the LMF.
8.2.3.2 Successful Operation
Figure 8.2.3.2-1: E-CID Measurement Report procedure, successful operation
The NG-RAN node initiates the procedure by sending an E-CID MEASUREMENT REPORT message. The E-CID MEASUREMENT REPORT message contains the E-CID measurement results according to the measurement configuration in the respective E-CID MEASUREMENT INITIATION REQUEST message.
The Measured Results IE shall be included in the E-CID Measurement Result IE of the E-CID MEASUREMENT REPORT message when measurement results other than the "Cell-ID" have been requested.
If available, the NG-RAN node shall include the NG-RAN Access Point Position IE or the Geographical Coordinates IE which is the configured estimated serving antenna position in the E-CID Measurement Result IE within the E-CID MEASUREMENT REPORT message. Upon reception of this NG-RAN Access Point Position IE, the LMF may use the value as the geographical position of the NG-RAN access point.
If available, the NG-RAN node shall include the Cell Portion ID IE in the E-CID MEASUREMENT REPORT message. Upon reception of the Cell Portion ID IE, the LMF may use the value as the cell portion for the measurement.
8.2.3.3 Unsuccessful Operation
Not applicable.
8.2.3.4 Abnormal Conditions
Void.
8.2.4 E-CID Measurement Termination
8.2.4.1 General
The purpose of E-CID Measurement Termination procedure is to terminate periodical E-CID measurements for the UE performed by the NG-RAN node.
8.2.4.2 Successful Operation
Figure 8.2.4.2-1: E-CID Measurement Termination procedure, successful operation
The LMF initiates the procedure by generating an E-CID MEASUREMENT TERMINATION COMMAND message.
8.2.4.3 Unsuccessful Operation
Not applicable.
8.2.4.4 Abnormal Conditions
Void.
8.2.5 OTDOA Information Exchange
8.2.5.1 General
The purpose of the OTDOA Information Exchange procedure is to allow the LMF to request the NG-RAN node to transfer OTDOA information to the LMF.
8.2.5.2 Successful Operation
Figure 8.2.5.2-1: OTDOA Information Exchange procedure, successful operation
The LMF initiates the procedure by sending an OTDOA INFORMATION REQUEST message. The NG-RAN node responds with OTDOA INFORMATION RESPONSE message that contains the available OTDOA information applicable to the relevant cells/TPs.
8.2.5.3 Unsuccessful Operation
Figure 8.2.5.3-1: OTDOA Information Exchange procedure, unsuccessful operation
If the NG-RAN node does not have any OTDOA information to report, the NG-RAN node shall respond with an OTDOA INFORMATION FAILURE message.
8.2.5.4 Abnormal Conditions
Void.
8.2.6 Positioning Information Exchange
8.2.6.1 General
The Positioning Information Exchange procedure is initiated by the LMF to request to the NG-RAN node positioning information for the UE. This procedure applies only if the NG-RAN node is a gNB.
8.2.6.2 Successful Operation
Figure 8.2.6.2-1: Positioning Information Exchange procedure, successful operation
The LMF initiates the procedure by sending a POSITIONING INFORMATION REQUEST message to the NG-RAN node.
If the Requested SRS Transmission Characteristics IE is included in the POSITIONING INFORMATION REQUEST message, the NG-RAN node may take this information into account when configuring SRS transmissions for the UE, and it shall include the SRS Configuration IE and the SFN Initialisation Time IE in the POSITIONING INFORMATION RESPONSE message.
If the Spatial Relation Information per SRS Resource IE and the Periodicity List IE are both included in the Requested SRS Transmission Characteristics IE, the NG-RAN node shall consider that the Spatial Relation per SRS Resource Item IE and the Periodicity List Item IE have one-to-one mapping relation.
If the UE Reporting Information IE is included in the POSITIONING INFORMATION REQUEST message, the NG-RAN node may take this information into account for allocating proper CG-SDT resources when positioning a UE.
If the UE TEG Information Request IE is included in the POSITIONING INFORMATION REQUEST message and set to "onDemand", the NG-RAN node shall, if supported, provide the UE Tx TEG association in the POSITIONING INFORMATION RESPONSE message.
If the UE TEG Information Request IE is set to "periodic", the NG-RAN node shall, if supported, reply with the POSITIONING INFORMATION RESPONSE message without including any UE Tx TEG association in this message. The NG-RAN node shall then periodically initiate the Positioning Information Update procedure for reporting the UE Tx TEG association, with the requested reporting periodicity.
8.2.6.3 Unsuccessful Operation
Figure 8.2.6.3-1: Positioning Information Exchange procedure, unsuccessful operation
If the Requested SRS Transmission Characteristics IE is included in the POSITIONING INFORMATION REQUEST message and the NG-RAN node is unable to configure any SRS transmissions for the UE, it shall respond with a POSITIONING INFORMATION FAILURE message. If a handover of the target UE has been triggered, the NG-RAN node shall send a POSITIONING INFORMATION FAILURE message with an appropriate cause value.
If the NG-RAN node is unable to provide any of the requested information, the NG-RAN node shall respond with a POSITIONING INFORMATION FAILURE message with an appropriate cause value.
8.2.6.4 Abnormal Conditions
Void.
8.2.7 Positioning Information Update
8.2.7.1 General
The Positioning Information Update procedure is initiated by the NG-RAN node to indicate to the LMF that a change has occurred in the SRS configuration or in the UE Tx TEG association. This procedure applies only if the NG-RAN node is a gNB.
8.2.7.2 Successful Operation
Figure 8.2.7.2-1: Positioning Information Update procedure, successful operation
The NG-RAN node initiates the procedure by sending a POSITIONING INFORMATION UPDATE message to the LMF. If the SRS Configuration IE is included in the POSITIONING INFORMATION UPDATE message, the LMF shall consider this information as the updated SRS Configuration for the UE. If the SFN Initialisation Time IE is included in the POSITIONING INFORMATION UPDATE message, the LMF shall consider this information as the SFN Initialisation Time associated to the SRS Configuration.
If the UE Tx TEG Association List IE is included in the POSITIONING INFORMATION UPDATE message, the LMF shall consider it as the UE Tx TEG association for the SRS resources that have changed their TEG association during the latest reporting interval.
8.2.7.3 Unsuccessful Operation
Not Applicable.
8.2.7.4 Abnormal Conditions
Void.
8.2.8 TRP Information Exchange
8.2.8.1 General
The purpose of the TRP Information Exchange procedure is to allow the LMF to request the NG-RAN node to provide detailed information for TRPs hosted by the NG-RAN node. This procedure applies only if the NG-RAN node is a gNB.
8.2.8.2 Successful Operation
Figure 8.2.8.2-1: TRP Information Exchange procedure, successful operation
The LMF initiates the procedure by sending a TRP INFORMATION REQUEST message. The NG-RAN node responds with a TRP INFORMATION RESPONSE message that contains the requested TRP information.
If the TRP List IE is included in the TRP INFORMATION REQUEST message, the NG-RAN node should include in the TRP INFORMATION RESPONSE message, the requested information for all TRPs included in the TRP List IE.
If the TRP List IE is not included in the TRP INFORMATION REQUEST message, the NG-RAN node should include the requested information for all TRPs hosted by the NG-RAN node in the TRP INFORMATION RESPONSE message
If the PRS Muting IE is included in the PRS Configuration IE in the TRP INFORMATION RESPONSE message, the LMF may take it into account as the muting information for the given PRS resource set.
If the QCL Info IE is included in the PRS Configuration IE in the TRP INFORMATION RESPONSE message, the LMF may take it into account for the given PRS resource list.
If the DL-PRS Resource Coordinates IE is included in the Geographical Coordinates IE in the TRP Information IE in the TRP INFORMATION RESPONSE message, the LMF may take it into account as the DL PRS Resource Coordinates relative to the TRP coordinate.
8.2.8.3 Unsuccessful Operation
Figure 8.2.8.3-1: TRP Information Exchange procedure, unsuccessful operation
If the NG-RAN node cannot provide any of the requested information for any TRP, the NG-RAN node shall respond with a TRP INFORMATION FAILURE message.
8.2.8.4 Abnormal Conditions
Void.
8.2.9 Positioning Activation
8.2.9.1 General
The Positioning Activation procedure is initiated by the LMF to request the NG-RAN node to activate semi-persistent or trigger aperiodic UL SRS transmission by the UE. This procedure applies only if the NG-RAN node is a gNB.
8.2.9.2 Successful Operation
Figure 8.2.9.2-1: Positioning Activation procedure, successful operation
The LMF initiates the procedure by sending a POSITIONING ACTIVATION REQUEST message to the NG-RAN node.
For semi-persistent UL SRS, the POSITIONING ACTIVATION REQUEST message includes an indication of the UL SRS resource set to be activated and may include the spatial relation for the semi-persistent UL SRS resource to be activated. For aperiodic UL SRS, if the SRS Resource Trigger IE is included in the POSITIONING ACTIVATION REQUEST message, the NG-RAN node shall take the value of this IE into account when triggering aperiodic SRS transmission by the UE.
If the Activation Time IE is included in the POSITIONING ACTIVATION REQUEST message, the NG-RAN node shall take the indicated value as the LMF’s requested time for activation of the UE’s SRS transmission.
Following successful activation of UL SRS transmission in the UE, the NG-RAN node shall respond with a POSITIONING ACTIVATION RESPONSE message. If the POSITIONING ACTIVATION RESPONSE message includes the System Frame Number and/or the Slot Number IEs, the LMF shall consider that the respective information indicates the activation time of SRS transmission by the UE.
8.2.9.3 Unsuccessful Operation
Figure 8.2.9.3-1: Positioning Activation procedure, unsuccessful operation
If the NG-RAN node is unable to activate UL SRS transmission in the UE, it shall respond with a POSITIONING ACTIVATION FAILURE message.
If the NG-RAN node is unable to trigger the aperiodic SRS transmission with the indicated SRS Resource Trigger IE, it shall respond with a POSITIONING ACTIVATION FAILURE message with an appropriate cause value.
8.2.9.4 Abnormal Conditions
Void.
8.2.10 Positioning Deactivation
8.2.10.1 General
The Positioning Deactivation procedure is initiated by the LMF to indicate to the NG-RAN node that UL SRS transmission should be deactivated in the UE. This procedure applies only if the NG-RAN node is a gNB.
8.2.10.2 Successful Operation
Figure 8.2.10.2-1: Positioning Deactivation procedure, successful operation
The LMF initiates the procedure by sending a POSITIONING DEACTIVATION message to the NG-RAN node. This message shall include an indication of the UL SRS resource set to be deactivated or release all the related resources.
8.2.10.3 Unsuccessful Operation
Not Applicable.
8.2.10.4 Abnormal Conditions
Void.
8.2.11 PRS Configuration Exchange
8.2.11.1 General
The PRS Configuration Exchange procedure is initiated by the LMF to request the NG-RAN node to configure or update (i.e., turn off) PRS transmission. This procedure applies only if the NG-RAN node is a gNB.
8.2.11.2 Successful Operation
Figure 8.2.11.2-1: PRS Configuration Exchange procedure, successful operation
The LMF initiates the procedure by sending a PRS CONFIGURATION REQUEST message to the NG-RAN.
If the PRS Configuration Request Type IE is set to “configure”, the NG-RAN node should use the information in the Requested DL PRS Transmission Characteristics IE to configure DL-PRS transmission by the indicated TRP(s).
If the PRS Configuration Request Type IE is set to “off”, the NG-RAN node should, if supported, use the information in the PRS Transmission Off Information IE to turn off the DL-PRS transmission for the indicated TRP(s), PRS Resource Set(s), or PRS Resource(s).
If DL-PRS transmission is successfully configured or updated for at least one of the TRPs, the NG-RAN node shall respond with a PRS CONFIGURATION RESPONSE message.
8.2.11.3 Unsuccessful Operation
Figure 8.2.11.3-1: PRS Configuration Exchange procedure, unsuccessful operation
If the NG-RAN node cannot configure or update DL-PRS transmission for any of the TRPs in the PRS TRP List IE of the PRS CONFIGURATION REQUEST message, it shall respond with a PRS CONFIGURATION FAILURE message with an appropriate cause value.
8.2.11.4 Abnormal Conditions
Void.
8.2.12 Measurement Preconfiguration
8.2.12.1 General
The Measurement Preconfiguration procedure allows the LMF to provide necessary information to the serving gNB and request the gNB to preconfigure measurement gap and/or PRS processing window for the UE. This procedure applies only if the NG-RAN node is a gNB.
8.2.12.2 Successful Operation
Figure 8.2.12.2-1: Measurement Preconfiguration procedure, successful operation
The LMF initiates the procedure by sending a MEASUREMENT PRECONFIGURATION REQUIRED message.
If the NG-RAN node is able to configure measurement gap or PRS processing window, it shall reply with the MEASUREMENT PRECONFIGURATION CONFIRM message.
8.2.12.3 Unsuccessful Operation
Figure 8.2.12.3-1: Measurement Preconfiguration procedure, unsuccessful operation
If the NG-RAN node cannot configure any of the measurement gap or PRS processing window, the NG-RAN node shall respond with a MEASUREMENT PRECONFIGURATION REFUSE message.
8.2.12.4 Abnormal Conditions
Void.
8.2.13 Measurement Activation
8.2.13.1 General
The Measurement Activation procedure is initiated by the LMF to request the NG-RAN node to activate or deactivate the preconfigured measurement gap or PRS processing window for the UE. This procedure applies only if the NG-RAN node is a gNB.
8.2.13.2 Successful Operation
Figure 8.2.13.2-1: Measurement Activation procedure, successful operation
The LMF initiates the procedure by sending a MEASUREMENT ACTIVATION message to the NG-RAN node.
If the PRS Measurement Info List IE is included in the MEASUREMENT ACTIVATION message, the NG-RAN node may take it into account when activating pre-configured measurement gap in the UE.
8.2.13.3 Unsuccessful Operation
Not Applicable.
8.2.13.4 Abnormal Conditions
Void.
8.3 Management Procedures
8.3.1 Error Indication
8.3.1.1 General
The Error Indication procedure is initiated by a node to report detected errors in one incoming message, provided they cannot be reported by an appropriate failure message.
8.3.1.2 Successful Operation
Figure 8.3.1.2-1: Error Indication procedure, LMF originated, successful operation
Figure 8.3.1.2-2: Error Indication procedure, NG-RAN node originated, successful operation
When the conditions defined in clause 10 are fulfilled, the Error Indication procedure is initiated by an ERROR INDICATION message sent from the receiving node.
The ERROR INDICATION message shall contain at least either the Cause IE or the Criticality Diagnostics IE.
8.3.1.3 Abnormal Conditions
Not applicable.
8.4 Assistance Information Transfer Procedures
8.4.1 Assistance Information Control
8.4.1.1 General
The purpose of the Assistance Information Control procedure is to allow the LMF to signal positioning assistance information to the NG-RAN Node for assistance information broadcasting. This procedure applies only if the NG-RAN node is a gNB.
8.4.1.2 Successful Operation
Figure 8.4.1.2-1: Assistance Information Control procedure
The LMF initiates the procedure by sending an ASSISTANCE INFORMATION CONTROL message.
If the Assistance Information IE is included in the ASSISTANCE INFORMATION CONTROL message, the NG-RAN Node shall, if supported, replace any previously stored assistance information and use the received information to configure assistance information broadcasting.
If the Broadcast Priority IE is included in the Assistance Information IE, the NG-RAN Node may take it into account when configuring broadcasting for the relevant information. Assistance information having the same Broadcast Priority value should receive the same treatment (i.e. broadcast by the NG-RAN Node or not broadcast).
If the Broadcast IE is included in the ASSISTANCE INFORMATION CONTROL message and set to "start", the NG-RAN Node may start broadcasting the assistance information. If the Broadcast IE is included in the ASSISTANCE INFORMATION CONTROL message and set to "stop", the NG-RAN Node may stop broadcasting the assistance information.
If the Positioning Broadcast Cells IE is included in the ASSISTANCE INFORMATION CONTROL message, the NG-RAN shall, if supported, consider that the received assistance information is applicable to the cells in this IE.
8.4.1.3 Abnormal Conditions
If the Broadcast IE is included in the ASSISTANCE INFORMATION CONTROL message and set to "start", and no assistance information is available, the NG-RAN Node shall consider the procedure as failed.
If neither the Assistance Information IE nor the Broadcast IE are included in the ASSISTANCE INFORMATION CONTROL message, the NG-RAN Node shall consider the procedure as failed.
8.4.2 Assistance Information Feedback
8.4.2.1 General
The purpose of the Assistance Information Feedback procedure is to allow the NG-RAN Node to give feedback to the LMF on assistance information broadcasting. This procedure applies only if the NG-RAN node is a gNB.
8.4.2.2 Successful Operation
Figure 8.4.2.2-1: Assistance Information Feedback procedure
If the Assistance Information Failure List IE is included in the ASSISTANCE INFORMATION FEEDBACK message, the LMF shall consider that assistance information broadcasting could not be configured for the relevant information.
If the Positioning Broadcast Cells IE is included in the ASSISTANCE INFORMATION FEEDBACK message, the LMF shall consider that the feedback provided is applicable to the cells in this IE.
8.4.2.3 Abnormal Conditions
Void.
8.5 Measurement Information Transfer
8.5.1 Measurement
8.5.1.1 General
The Measurement procedure allows the LMF to request one or more TRPs in the NG-RAN node to perform and report positioning measurements. This procedure applies only if the NG-RAN node is a gNB.
8.5.1.2 Successful Operation
Figure 8.5.1.2.1: Measurement procedure. Successful operation.
The LMF initiates the procedure by sending a MEASUREMENT REQUEST message to the NG-RAN node, indicating in the TRP Measurement Request List IE the TRP(s) from which measurements are requested. The NG-RAN node shall use the included information to configure positioning measurements by the indicated TRP(s). If at least one of the requested measurements has been successful for at least one of the TRPs, the NG-RAN node shall reply with a MEASUREMENT RESPONSE message including the TRP Measurement Response List IE.
If the Report Characteristics IE is set to "OnDemand", the NG-RAN node shall return the corresponding measurement results in the MEASUREMENT RESPONSE message, and the LMF shall consider that this reporting has been terminated by the NG-RAN node. If the Report Characteristics IE is set to "Periodic", the NG-RAN node shall initiate the corresponding measurements, and it shall reply with the MEASUREMENT RESPONSE message without including any measurement results in the message. The NG-RAN node shall then periodically initiate the Measurement Report procedure for the corresponding measurements, with the requested reporting periodicity.
If the Measurement Beam Information Request IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall include the Measurement Beam Information IE in the TRP Measurement Result IE of the MEASUREMENT RESPONSE message.
If the Measurement Quality IE is included in the TRP Measurement Result IE in the MEASUREMENT RESPONSE message, the LMF may take it into account as the TRP estimate of the measurement quality. If the Measurement Quality IE includes the Zenith Quality IE, the LMF may take it into account within the angle measurement quality.
If the Timing Reporting Granularity Factor IE is included in the TRP Measurement Quantities IE in the MEASUREMENT REQUEST message, the NG-RAN node may take it into account when configuring measurements including UL RTOA and gNB Rx-Tx Time Difference.
If the System Frame Number IE and/or the Slot Number IE are included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, consider that the respective information indicates the activation time of SRS transmission.
If the Report Characteristics IE is set to "OnDemand" and the Response Time IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, return the corresponding measurement results in the MEASUREMENT RESPONSE message within the indicated time.
If the Measurement Characteristics Request Indicator IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, take the requested measurement characteristics into account when configuring measurements, and include the requested information, if available, in the MEASUREMENT RESPONSE message.
If the Number of TRP Rx TEGs IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, use it to measure the same SRS resource with different TRP Rx TEGs for the indicated TRP, and report the corresponding UL-RTOA and/or gNB Rx-Tx time difference measurements.
If the Number of TRP RxTx TEGs IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, use it to measure the same SRS resource with different TRP RxTx TEGs with the same TRP Tx TEG for the indicated TRP, and report the corresponding gNB Rx-Tx time difference measurements.
If the Measurement Time Occasion IE is included in the MEASUREMENT REQUEST message, the NG-RAN node may take it into account as the number of SRS measurement time occasions for a measurement instance.
Interaction with the Measurement Report procedure:
If the Report Characteristics IE is set to "Periodic" and the Measurement Amount IE is included in the MEASUREMENT REQUEST message, the NG-RAN node shall, if supported, take it into account for sending the MEASUREMENT REPORT message.
8.5.1.3 Unsuccessful Operation
Figure 8.5.1.3.1: Measurement procedure. Unsuccessful operation.
If the NG-RAN node cannot configure any of the requested measurements for any of the TRPs in the TRP Measurement Request List IE of the MEASUREMENT REQUEST message, it shall respond with a MEASUREMENT FAILURE message with an appropriate cause value.
8.5.1.4 Abnormal Conditions
If the Report Characteristics IE is set to "OnDemand" and the Response Time IE is included in the MEASUREMENT REQUEST message but the NG-RAN node is unable to provide the measurement results within the indicated time, the NG-RAN node shall, if supported, respond with a MEASUREMENT FAILURE message with an appropriate cause value.
8.5.2 Measurement Report
8.5.2.1 General
The Measurement Report procedure allows the NG-RAN node to report positioning measurements to the LMF. This procedure applies only if the NG-RAN node is a gNB.
8.5.2.2 Successful Operation
Figure 8.z.2.2.1: Measurement Report procedure. Successful operation.
The NG-RAN node initiates the procedure by sending a MEASUREMENT REPORT message to the LMF. The MEASUREMENT REPORT message contains the measurement results according to the associated measurement configuration.
8.5.2.3 Abnormal Conditions
Void.
8.5.3 Measurement Update
8.5.3.1 General
The Measurement Update Procedure allows the LMF to notify the NG-RAN node of a change in a previously configured measurement. This procedure applies only if the NG-RAN node is a gNB.
8.5.3.2 Successful Operation
Figure 8.5.3.2.1: Measurement Update: Successful Operation.
The LMF initiates the procedure by sending a MEASUREMENT UPDATE message.
If the SRS Configuration IE is included in the MEASUREMENT UPDATE message, the NG-RAN node shall overwrite the previously stored SRS configuration.
If the AoA Search Window Information IE is included in the TRP Measurement Update List IE in the MEASUREMENT UPDATE message, the NG-RAN node shall clear any previously stored AoA search window information and store the newly received information.
If the Number of TRP Rx TEGs IE is included in the TRP Measurement Update List IE in the MEASUREMENT UPDATE message, the NG-RAN node shall clear any previously stored information and store the newly received information.
If the Number of TRP RxTx TEGs IE is included in the TRP Measurement Update List IE in the MEASUREMENT UPDATE message, the NG-RAN node shall clear any previously stored information and store the newly received information.
If the Measurement Characteristics Request Indicator IE is included in the MEASUREMENT UPDATE message, the NG-RAN node shall clear any previously stored information and store the newly received information.
If the Measurement Time Occasion IE is included in the MEASUREMENT UPDATE message, the NG-RAN node shall clear any previously stored information and store the newly received information.
8.5.3.3 Unsuccessful Operation
Not applicable.
8.5.3.4 Abnormal Conditions
If the NG-RAN node cannot identify at least one of the previously requested measurement to be modified, it shall consider the procedure as failed and initiate local error handling.
8.5.4 Measurement Abort
8.5.4.1 General
The purpose of the Measurement Abort Procedure is to enable the LMF to abort an on-going measurement. This procedure applies only if the NG-RAN node is a gNB.
8.5.4.2 Successful Operation
Figure 8.5.4.2.1: Measurement Abort Procedure: Successful Operation.
The LMF initiates the procedure by sending a MEASUREMENT ABORT message.
Upon receiving this message, the NG-RAN node shall terminate the on-going measurement identified by the LMF Measurement ID IE and may release any resources previously allocated for the same measurement.
8.5.4.3 Unsuccessful Operation
Not applicable.
8.5.4.4 Abnormal Conditions
If the NG-RAN node cannot identify the previously requested measurement to be aborted, it shall ignore the MEASUREMENT ABORT message.
8.5.5 Measurement Failure Indication
8.5.5.1 General
The Measurement Failure Indication procedure allows the NG-RAN node to notify the LMF that the measurements previously requested with the Measurement procedure can no longer be reported. This procedure applies only if the NG-RAN node is a gNB.
8.5.5.2 Successful Operation
Figure 8.5.5.2.1: Measurement Report procedure. Successful operation.
Upon reception of the MEASUREMENT FAILURE INDICATION message, the LMF shall consider that the indicated measurements have been terminated by the NG-RAN node.
8.5.5.3 Abnormal Conditions
Void.